CLIENT

Iron Mountain

Iron Mountain

Iron Mountain

OVERVIEW

Iron Mountain (NYSE:IRM) contracted with NextEra to install 7.2 MW of solar on a data center in New Jersey, the largest rooftop solar system on a data center in the US. The system generates clean energy for Iron Mountain’s data center through a PPA. Construction started in Fall 2019 and is expected to be complete by the end of the year. Black Bear Energy represented Iron Mountain throughout the process from concept to commissioning.

Project Benefits:

Energy Cost Savings

Project Type:

Solar

System Size:

7.2 MW

Location:

NJ

Date Commissioned:

2019/Ongoing